Context
The full ULIP infrastructure, around 90 virtual machines, is planned to move to the National Government Cloud (NGC). Leadership needs a clear cost picture to make the infrastructure decision.
My role
Driving cost estimation and migration planning. Seat: PO.
What I did
  • Driving cost estimation and planning for the move of ~90 VMs to NGC.
  • Modelling assumptions and rate cards to support leadership's infrastructure decision.
Outcome
[ADD: decision or current status of the migration]